10.07.2008

Navigation equipment facilities. Leading marks in approach channel

Passenger sea terminal on Vasilyevsky island in Saint-Petersburg

10.10.2007 - 07.07.2008

Construction period

FSUE «Rosmorport»

Client

Description

The structures are solid reinforced-concrete raft on hydrotechnical foundation made of 12 inclined (1:3) pile shells with diameter of 1,220 mm and length of 38.5 and 28.0 m. Leading marks are equipped with light-optical equipment installed on bearing structures.

The scope of work

  • Total volume of laid concrete is 420 m³.

Features of the object

  • Severe weather conditions

    Work on high-precision pile driving was carried out during storms.

  • Difficult logistic conditions

    Delivery of concrete mortar and its timely installation was carried out in the open sea.

  • Open sea

    All work was carried out at a distance of 7 km from the coastline of the Gulf of Finland.

Navigation equipment facilities. Leading marks in approach channel

Passenger sea terminal on Vasilyevsky island in Saint-Petersburg