12.03.2019
Construction of «Liquefied natural gas transshipment quay of Terminal for LNG production and transshipment»
Vysotsk port, Leningrad oblast
05.05.2017 - 03.03.2019
Construction period
LLC Kriogaz-VysotskClient
The scope of work
- Arrangement of quay pile foundation — installation with soil drilling out, as well as arrangement of reinforcement cages, sand filling and concreting of cavity for 143 pcs (2,000 t) of pile shells Ø1,420×16 mm along 1,408 lm of drilling.
- Arrangement of the quay superstructure, concreting — 4,700 m³.
- Arrangement of metal frameworks and passages, mounting of quay equipment — fenders, self-detachable hooks.