Marine Passenger Terminal on Vasilievsky Island (Saint-Petersburg)

Заказчик строительства: ФГУП «Росморпорт»
Подрядчик (субподрядчик): ЗАО «ГТ Морстрой»
Период строительства: 09.2006-12.2006 г
Address: Россия, Санкт-Петербург

This is a monolithic reinforced concrete bulkhead (the total volume of placed concrete is 420 cubic meters) on the hydrotechnical foundation of 12 inclined (1: 3) pile shells with a diameter of 1220 mm and lengths of 38.5 and 28.0 m.

The light-optical equipment is installed on the leading beacons support structures.

The complexity of this construction was the need for high-precision pile driving at a distance of about 7 km from the coastline to the water area of the Gulf of Finland during the storms, as well as in delivering the concrete solution to the open sea and its timely laying.

Due to the use of modern equipment and excellent engineering training of personnel, the construction was completed in good time.