Construction of quays № 2, 3 at the facility: Logistics and industrial park of mineral fertilizers at Ust-Luga port

Customer: Ultramar LLC

Period: February 2021

Facility: "Range of works on construction of quays № 2, 3 at the facility: Logistics and industrial park (complex) for storage and transshipment of mineral fertilizers with storage facilities and rail infrastructure at the municipal settlement “Vistino village settlement” of the municipal entity Kingisepp municipal district of the Leningrad Region. Marine shipment terminal" 

Completion is nearing!

FEBRUARY 2021 saw the following kinds of operations performed:

- Grouting capping – 292.22 cubic m.


- Installing bollards 100 TONS - 11 pcs.


- Installing bollards 125 TONS:

• drilling wells, 56 mm in diameter - 28 pcs. (31.1 m bore bit.)

• filling up wells – 33.55 cubic dm.

• installing anchor bolts - 28 pcs.


- Installing fenders - 18 pcs.:

• drilling wells,35 mm in diameter - 720 pcs. (201.6 m bore bit)

• drilling wells, 42 mm in diameter - 480 pcs. (196.8 m bore bit)

• drilling wells, 48 mm in diameter - 240 pcs. (144 m bore bit)

• filling up wells – 188.19 cubic dm.

• installing anchor bolts М30 - 432 pcs.

• Installing anchor bolts М36 - 288 pcs.

• Installing anchor bolts М42 - 144 pcs.


- Building bulkheads in the ducts of the utilities networks – 19.85 cubic m.

As well as other kinds of activities!